IMPORTANT NOTICE
September 16, 2022
The Ayer DPW will be reclaiming the following streets beginning Monday September 19th:
Pleasant Street – from 62 Pleasant Street to Howard Street
Page Street – from Groton Harvard Road to East Main Street
The process involves a pavement reclaiming machine that creates a new base material by grinding the existing asphalt and mixing it with the existing base material. The reclaiming is scheduled to begin on Monday, September 19, 2022, weather permitting. The work on Pleasant Street is anticipated to take two days and work on Page Street one day.
A detour will be in place on Pleasant Street during work hours, but the road will be open to local traffic.
The detour for Pleasant Street will divert traffic to Jackson Street. Please see attached image of the detour.
Page Street will be closed to through traffic but open to local traffic.
No on-street parking will be allowed during the reclaiming operation (approximately 7:00 AM to 4:00 PM).
During construction, there will be varying road conditions. Please travel with caution.
Police details will be onsite to direct traffic and construction signage will be in place.
If you have any questions, please contact the Department of Public Works at 978-772-8240.
Original source can be found here.